Information Technology

Crown Courts

Crown Courts, Nationwide

Client

Completion Date
2003-2005
Value
Confidential
Services
Project Management
Site Management and Design Services

Architects

Location
Various crown courts across the UK
Completion
On time under budget




Inner London Crown Court

Inner London Crown Court

Project Overview

Update and computerisation of Crown Courts across the UK. Works were completed in occupation and required refurbishment skills in order to complete the works to English Heritage standards.

Project details and pictures



Fuji Bank

Fuji Bank, London

Client
Fuji Bank
Completion Date
1999
Value
Confidential
Services
Project Sponsorship
Project management of Relocation and IT

Architects

Location
London
Completion
On time under budget




Fuji Bank

Fuji Bank

Project Overview

Project managing to BS6079 the complete move of the Bank’s European data centre. This included a survey of suitable locations, analysing costs, initial contract negotiations and the detailed listing of existing equipment in the Bank’s present premises.



Lloyds TSB

Lloyds TSB, London

Client
Lloyds TSB
Completion Date
1999
Value
Confidential
Services
Project Management
Architects

Location
London
Completion
On time under budget

Project Overview

Litchfield undertook a detailed survey project of the UK LAN network, deciding on the criteria to be checked, organising the teams and ensuring that progress met its target of five sites a day across the UK.

Following Project 1, the team was retained for the LAN upgrade project, which involved the installation of various LAN fixes using Cisco equipment. This was completed ensuring no loss of business or delay to the desktop rollout.



Merrill Lynch

Merrill Lynch, Broadgate, London

Client
Merrill Lynch
Completion Date
2000
Value
Confidential
Services
Project Management
Architects

Location
London
Completion
On time under budget




Broadgate, Liverpool Street

Broadgate, Liverpool Street

Project Overview

Litchfield Projects managed the design and installation of the SAN for the customer on behalf of IBM, where project life cycle and risk planning were required.

This involved designing and implementing a documentation survey to discover a base for the commencement of the establishment of the SAN, consolidating 1,000 servers and installing a resilient MAN between seven centres. The data was then transferred to the new office complex where it was taken over by IBM’s managed service teams.



Mizuho International

Mizuho International

Client
Mizuho International
Completion Date
2002
Value
Confidential
Services
Project Management
Architects

Location
London
Completion
On time under budget


Bracken House

Bracken House

Project Overview

Litchfield was appointed as independent project managers for the Mizuho project. This involved the procurement of services, the construction teams, and organising all aspects of the project to complete it on time, to specification and on budget.

Project details and pictures



Orange

Orange

Client
Orange
Completion Date
20005
Value
Confidential
Services
Project Management
Site Management and Design Services

Architects

Location
London
Completion
On time under budget



Project Overview

This project involved managing the creation of the Customer Services contingency plan. It included analysing and procuring all resources on behalf of Orange, the co-ordination and assimilation of the Customer Service plan into the Y2K plan, and ensuring back plans were tested and in place. The requirements and duties were conveyed to all parties and complied with. This required the management of the complete project lifecycle.



PSI Net

Litchfield was required to upgrade this building to Telehouse standards. Each floor included a variety of tenants from ISPs to switch centres. We dealt with numerous IT tenants, the completion of the landlord’s defects works and the construction of the ISP centre areas.



QBE Management

The project comprised a 50,000 square feet Category A and Category B fit out. However, this was increased to 100,000 square feet fit-out part way through the project due to a merger. This involved the re-design of half the original scheme.

Litchfield completed the revised scheme under a construction management route within the original programme and completed on schedule. The project was also completed under budget.



Sumitomo Bank

Sumitomo Bank, European Data Centre

Client
Sumitomo Bank
Completion Date
1999
Value
£1.2 million
Services
Project Management
Architects and Consultants
IBM UK/Elando Designs
Location
Keybridge House, Vauxhall, London
Completion
On time under budget

Project Overview

This project involved the complete project life-cycle move of the Bank’s European data centre, including contract negotiations and the creation of two new disaster recovery sites. It also required the design and construction of the data centre, implementation and testing of the new networks and applications.

Project details and pictures